🔍 Explorer
Distinguishes (a) all physical paths, (b) energized source-to-load paths through closed devices and the selected ATS source, and (c) paths blocked by open devices.
⚖️ Load Aggregation / Energized Load Summary
This is NOT a Newton-Raphson power-flow study. Assumptions:
- Balanced 3-phase, lossless transformers and conductors
- Loads are aggregated upstream radially. Loops are not solved.
- Transformer kVA is conserved across primary/secondary. Current is recomputed at each side voltage.
- Panels use either a user-supplied demand (kW/kVAR/PF) or an “assumed load current” (not the breaker rating).
- Motors compute steady-state load only when running. Inrush is a separate simulation.
- Source impedance and voltage drop are not modeled.
Preset Systems & Challenges
Load a preset topology, then explore it in the Builder, Explorer, and Load Aggregation tabs.
Simple Radial System
Utility 13.8kV → 13.8/0.48kV transformer → main bus → feeder breakers to motor and step-down 480/208 transformer feeding a panel.
Beginner9 ComponentsRing Bus (Tie Normally Open)
Two utility sources, two bus sections, tie breaker normally open so only one source feeds at a time. Closing the tie creates parallel sources (intentional warning).
Intermediate8 ComponentsIndustrial Plant
13.8kV utility, 2 MVA main XFMR to 480V switchgear, MCC with motors, capacitor bank, and 480/208 step-down for lighting panel.
Advanced13 ComponentsEmergency Power (ATS)
Normal utility and emergency generator with ATS. Normal source selected by default. 480/208 transformer before critical 208V panel.
Intermediate10 ComponentsCommercial Building
13.8kV utility, 13.8/0.208 kV step-down transformer, 208V main switchboard, three 208V panels.
Beginner7 ComponentsAbout This Tool
The one-line (single-line) diagram is the primary communication tool of power systems engineering, and reading or building one accurately is a foundational skill. This educational builder lets you draw one-line diagrams and inspect them with a simplified balanced 3-phase model. It performs load aggregation (sum of downstream loads as kW/kVAR/kVA and per-side currents), honors open breakers/fuses/disconnects and ATS source selection, and warns when basic engineering rules are violated.
What You’ll Learn
- Place and connect standard one-line diagram symbols for sources, transformers, breakers, buses, and loads
- Trace energized paths from source to load through radial, ring-bus, and ATS system topologies
- Explain how an open breaker or an ATS in transfer position changes the energized path in a system
- Aggregate load demand from individual loads through distribution equipment to the source
- Identify the key differences between simple radial, main-tie-main, and ring-bus topologies
- Read and interpret a one-line diagram connection map and equipment list
Symbols
How to Use
- Drag equipment from the sidebar onto the canvas (or click a palette item to place it).
- Click and drag a port (blue dot) to another port to make a connection.
- Right-click equipment to edit, rotate, toggle open/closed, switch ATS source, or start/stop motors.
- Press R to rotate the selected equipment 90°; Delete removes it.
- Toggle Load Aggregation to see kW/kVA/A on equipment and connections.
- Toggle Energized Connectivity to color the wires that are actually energized.
- Run Self-Tests (header button) to verify the computation engine — your diagram is preserved.
Cable Ampacity (NEC 310.16)
Cable elements carry the raw table ampacity from NEC Table 310.16 (not more than three current-carrying conductors in raceway, cable, or earth, 30°C ambient) for the chosen size, material, and insulation temperature rating, multiplied by the number of parallel sets. Ambient-temperature and conductor-count adjustment factors are not modeled. Remember that NEC 240.4(D) separately limits the overcurrent device for small conductors (14/12/10 AWG copper → 15/20/30 A; 12/10 AWG aluminum → 15/25 A) regardless of insulation rating — that is an overcurrent-protection rule, not an ampacity.
Common Mistakes
- Connecting a 208 V panel directly to a 480 V bus without a step-down transformer — flagged even when a cable sits in between.
- Treating an ATS as having “two outputs” — it has two inputs (Normal, Emergency) and one output.
- Confusing a breaker’s rating with the actual branch load current.
- Computing connection current using the wrong side voltage of a transformer.